When you change the due date of a task, you can choose to notify the assignees about this change. By doing so, you can make sure that they prioritize their work properly and deliver it on time.
Procedure
-
Go to
click the name of the appropriate project, and then select the tasks whose due date you want to change.
-
Select
-
In the
Change Task and Step Due Dates dialog box, select
Set Expected Duration or
Set Due Date, and then enter the expected duration of the tasks or task steps (in days or hours) or their due dates (by clicking the calendar icon).
Tip: You can set the expected duration or the due date for the tasks themselves or for each task step.
-
Choose whether or not you want assignees to receive automatic email notifications.
By default, assignees receive an automatic email notification after you change one or more due dates. If you do not want them to receive automatic email notifications, clear the
Send email to assignees check box.
Important: For email notifications to be delivered, ask your
WorldServer administrator to make sure that:
- The assignees have valid email addresses.
- Notification delivery () is configured properly on your environment.
- The notification engine is enabled on your environment (
notification_engine=on in the
general.properties file).
Administrators can also change the content of the automatic email notification by going to
and selecting
Task Due Date Changed or
Task Step Due Date Changed in the
Notification Type list.
-
Click
OK.